Can you add the quenching and tempering furnace outputs to calculate mesh belt line throughput?

Published苏能工业炉工程技术团队&唐荔

No. The same workpieces pass through quenching and then tempering. Adding the weights quoted for the two furnace stages counts the same batch twice. To calculate how many kilograms of quenched-and-tempered parts the line can produce per hour, measure the same batch after it has completed tempering.

Where are the three output figures stated in the agreement?

One roller-supported mesh belt line agreement from Jiangsu Suneng Industrial Furnace Co., Ltd. (Suneng) lists throughput separately for the quenching furnace, the tempering furnace and final acceptance.

Where to lookWording for this projectWhat the entry answers
Quenching furnace parameter tableApproximately 150 kg/hWhat throughput is the upstream stage configured for?
Tempering furnace parameter table150 kg/hWhat throughput is the downstream stage configured to receive?
Final acceptance clause at the buyer's siteApproximately 150 kg/hWhat throughput condition is agreed for acceptance?
One batch, two stages. Do not add the furnace outputs. Quenching parameters; Approx. 150 kg/h. Tempering parameters; 150 kg/h. Final on-site acceptance; Approx. 150 kg/h. The first two entries are equipment parameters. The last is the agreed acceptance condition.

Of the two furnace parameter tables, only the quenching furnace table uses “approximately” before its output. The final acceptance clause separately specifies approximately 150 kg/h and states that actual output depends on workpiece shape and dimensions, unit weight, loading and process requirements. Preserve all three original formulations in a quotation comparison so you can distinguish equipment parameters from the conditions proposed for acceptance.

Where should you weigh output when scheduling the full order?

If the order requires both quenching and tempering, weight measured at the quenching furnace outlet tells you only how much the upstream stage has discharged. To establish how much has completed both stages, agree with the supplier on the weighing point after tempering and state the workpiece and loading arrangement to be used.

Ask both suppliers to use the same representative part and fill in separate rows for the quenching stage, tempering stage and whole-line acceptance conditions. Check equipment capability stage by stage, and check order throughput through the final process required by the buyer.

Website case · Stage-by-stage throughput in a roller-supported mesh belt quench and temper line https://www.jssngyl.cn/en/case/roller-belt-stage-output