To judge the quality of mesh belt furnace, first look at whether it can complete the process under the agreed workpiece, belt loading, temperature, atmosphere and cycle time, and then match the design basis, equipment record and acceptance requirements of the furnace body lining, heating temperature control, mesh belt support, transmission tension and guidance. When encountering belt mistracking, first clarify the location, the working condition and recent changes, and then check the equipment files of the corresponding parts.
This article first lists the procurement and diagnostic materials. For specific inspection, measurement and adjustment methods, the responsible personnel need to check the instructions, drawings and maintenance procedures of the equipment, and do not provide in-operation adjustment instructions or unified adjustment quantities.
Define the operating conditions for acceptable performance
Different workpieces and processes have different requirements for equipment. Before purchasing, write down the material, size, single piece quality, belt loading method, unit time feeding amount, process temperature and time, atmosphere, cooling and upstream and downstream interfaces. When comparing equipment, use the same set of working conditions and supply range.
Small parts that can stabilize tiling or controlled stacking can be evaluated in the mesh belt furnace scheme; workpieces that are easy to lag, roll down, severely stacked or need special support should be checked first. It cannot be determined that it is suitable for this project based on the name of the furnace, the width of the mesh belt or the appearance alone.
Link structural design, records and acceptance
The furnace shell, furnace lining and heating elements are worth checking, but the material brand or brand cannot prove the quality of the whole machine alone. It is necessary to ask whether the material selection corresponds to the long-term temperature, atmosphere, load and maintenance conditions, and whether the configuration is consistent with the workpiece process.
The mesh belt speed, effective heating length and process time need to be checked together; loading and support, cooling and front and rear processes should also be matched. If the parameters of a certain component are suitable, it does not mean that the whole line has reached a stable accepted output.
| Check the items | What information do you need first? | What is used to judge? |
|---|---|---|
| Workpiece and belt loading | Material, size, single-piece quality, number of belt loading layers, feeding record | Whether the workpiece is suitable for this conveying method, and whether the scheme uses the same working condition. |
| Furnace body and furnace lining | Structural description, material list, applicable temperature area and maintenance documents | Whether the material selection and structure base covers the agreed conditions |
| Heating and temperature control | Temperature zone layout, process requirements, temperature control records and agreed test methods | Whether the temperature zone and time correspond to the process, and whether the test evidence can be traced |
| Mesh belt, support and transmission | Mesh belt material, support method, transmission and tension structure, loading conditions | Whether the continuous conveying configuration matches the load, and whether the maintenance responsibility is clear |
| Whole line and delivery | Including items such as cooling, cleaning or tempering, interface lists and acceptance documents | What equipment does the quotation cover, and who is responsible for the capabilities and final acceptance of each section? |
This table is used to compare the completeness of the scheme and information. It is not a unified material specification, nor does it replace the technical agreement of specific equipment.
For belt drift, record the symptom, equipment arrangement and recent changes
First, sort out the existing records: belt mistracking occurs in the feeding, furnace, discharge or return position; whether it occurs at the same time as a certain workpiece, belt loading state or replacement time; whether to replace the mesh belt, adjust the support, maintain the transmission or change the feeding method recently. Without these backgrounds, it is difficult to confirm the reason by "mesh belt to one side" alone.
Then compare with the actual structure of the equipment. The old information mentioned the head and tail rollers, rollers and bearing seats; the current mesh belt equipment may also use sprockets, guides and other support arrangements, which should be subject to the drawings of the machine, and the adjustment method of the general conveyor belt should not be directly transferred to all mesh belt furnaces.
| Data check parts | What materials do you bring? | What needs to be confirmed with the person in charge of the equipment? |
|---|---|---|
| Mesh belt and joint | Mesh belt specifications, replacement records, existing status photos | Whether it is consistent with the original design, and whether there is any change before and after the abnormality |
| Support and load | Support layout, belt loading method, feeding record | Whether the conditions of use correspond to the design, and whether the problem changes with loading |
| Transmission and tension | Transmission diagram, tension structure description, maintenance record | What is the structure of this machine, and what data needs to be verified according to the device file? |
| Head and tail guidance and return | Relevant drawings, existing inspection or maintenance records | Which real parts correspond to the abnormal position? It cannot be judged only by the general diagram. |
| Input and output interface | Record of loading and unloading material arrangement, replacement and abnormal occurrence | Is there a phenomenon that occurs at the same time as the change of conveying connection and belt loading? |
These are data check items, not all devices to carry out the same on-site operation one by one. The specific measurement position, allowable deviation and processing order should be confirmed by the responsible person according to the local file.
Specify equipment tests and product results separately
Procurement acceptance should first agree on the conditions of workpiece, belt loading, process, continuous operation and supply interface, and then write down the test item, recording method, judgment basis and responsibility. Equipment temperature control or conveying test and workpiece quality inspection correspond to their respective requirements, and there is no need to record a single record to replace all the results.
When the existing equipment needs to be repaired, keep the work condition, maintenance and abnormal records before and after the problem; when purchasing new equipment, the supplier is required to match the material selection, configuration, interface, test and delivery materials to the same version of the scheme. The evidence that has not been obtained is listed as pending confirmation and should not be supplemented by verbal "good quality" or fixed energy-saving percentage.
What to prepare for a technical enquiry
Prepare workpiece and belt loading information, process requirements, target cycle time, equipment model and drawings, belt mistracking location and existing records. First judge whether it is the selection of new equipment, the existing transportation problem, or whether it involves the process and the whole line interface at the same time, and then organize the technical communication.
Can be compared The applicable conditions of the workpiece and process of mesh belt furnace, use again What parameters are required for the quotation of industrial furnaces? (in Chinese) Sort out the inquiry input. The product page is the manufacturer's public plan description, and the specific ability and acceptance results still need to be confirmed by the project information.