The approximately 300 kg/h in this protective-atmosphere oil-quench and temper line agreement from Jiangsu Suneng Industrial Furnace Co., Ltd. (Suneng) refers to small and medium-sized metal parts passing through the entire line, including tempering and post-tempering cooling. When checking your quotation, first find the heading under which the figure appears. If throughput is listed only under the quenching furnace, ask for a separate whole-line figure covering the final process stage.
Find the throughput entry and then identify the last process stage
In this project, parts are loaded and heated in the protective-atmosphere quenching furnace, then pass through the oil tank, oil draining, washing, tempering and post-tempering cooling. The main furnace belt is 500 mm wide and the heated section is 4700 mm long. These dimensions describe the upstream quenching furnace. The complete line also includes the downstream equipment.
| How another supplier presents its quotation | What the buyer should ask |
|---|---|
| Throughput appears under “quenching furnace” | What whole-line throughput applies after washing, tempering and final cooling? |
| Throughput appears under “complete line” | Where does this line begin and which process stage is its endpoint? |
| A separate continuous operating duration is stated | How are continuous operation and loaded throughput each tested? |
What does a 24-hour continuous run verify?
This agreement includes “24 hours of continuous, fault-free equipment operation” in the on-site acceptance requirements and separately requires checking the equipment's processing condition. Test duration and the daily quantity of conforming parts are separate measures. To determine the latter, you also need the actual loaded operating time, weighing point and criteria for conforming workpieces. Multiplying hourly throughput directly by the acceptance-test duration treats the entire test period as fully loaded production.
For your own quotation, copy the throughput entry together with its equipment heading, then copy the last process stage in the equipment list. This gives the supplier enough context to explain the measurement endpoint without sending the whole quotation.
Website case · Whole-line throughput of a protective-atmosphere oil-quench and temper line https://www.jssngyl.cn/en/case/overseas-oil-quench
Telephone: 13052986814
Email: 997518512@qq.com
Technical authors: Suneng Industrial Furnace Engineering Team & Tang Li