For 650 tonnes of quenched bars per month, how much must a fork-handling furnace charge per batch?

Published苏能工业炉工程技术团队&唐荔

At 26 production days and 3 batches per day, each batch must deliver about 8.33 tonnes of accepted bars. A Jiangsu Suneng Industrial Furnace Co., Ltd. fork-handling rapid-quench furnace proposal gives an 8–10 tonne charge excluding support blocks, a target of 650 tonnes per month and 20 working hours per day. The 26 days and 3 batches per day are scheduling assumptions used here.

Put the monthly target on an actual calendar

At 26 days and 20 scheduled hours per day, 650 tonnes means 25 tonnes per day or 1.25 tonnes per scheduled hour. The 26 days are an example. With an unchanged daily batch count, fewer production days require more net weight per batch. If orders count accepted product only, allow for rework and scrap.

Monthly target, batch load and transfer time in the proposal

ItemConditionPurchasing check
650 tonnes per monthTarget capacityAgree whether to count accepted net weight or total processed weight.
8–10 tonnes per batchProposed load excluding support blocksCheck net weight for the actual combination of bars.
Approximately 45 secondsProposed transfer from furnace to waterThis covers transfer only, not the complete batch cycle.

How much of the charge will ship as accepted product?

This schedule gives 78 batches per month. Dividing 650 by 78 gives approximately 8.33 tonnes of accepted bars per batch. Divide by the accepted yield by weight to find the necessary charge. At a 95% yield, charge approximately 8.77 net tonnes per batch. Charging only 8 tonnes for 78 batches gives at most 624 tonnes, even at full yield, leaving a 26-tonne shortfall.

Monthly target converted to a batch load
At 26 days per month, 3 batches per day and 95% accepted yield by weight, the required average net charge is about 8.77 tonnes per batch.

Calculation sequence: monthly target → available days → achievable batch count → required net accepted weight per batch → compare with actual loading and inspection records.

Can three batches fit into 20 hours?

Three consecutive batches on one furnace allow an average of 6 hours 40 minutes each, including loading, heating, soaking, discharge and necessary waiting. Reschedule the monthly product mix if a size needs longer soaking. The daily average helps reveal a gap. A production schedule must also account for batches spanning shifts and for starts and stops.

Bar lengths, diameters and grades affect loading and the required process. Link the net charge, complete cycle time and inspection results by batch number. An acceptance test covering a few batches documents those runs and sizes. Use the agreed calendar for projections and a full month of records for actual monthly output.

Which data are most useful for checking the target?

Start with a loading drawing and one full cycle record for the main bar size, plus its share of monthly orders. These show whether the shortfall comes from net batch weight, process time or too few days allowed for downtime.

Source: 2025 proposal for the high-temperature chamber furnace with fork handling, sections 1, 2 and 4. The 26 production days, 3 batches per day and 95% accepted yield are example assumptions.