Can four copper-alloy wire annealing chambers share one charging car?

Published苏能工业炉工程技术团队&唐荔

Yes, provided the schedule works on the busiest shift. A Jiangsu Suneng Industrial Furnace Co., Ltd. copper-wire annealing contract lists four chambers, one fork charging car, one loading station and one unloading station. Plot the discharge times together. Where two furnaces call for the car at once, or the previous batch still occupies the unloading station, check whether the operations can be staggered within the permitted process windows.

Four chambers can heat at once. The car can serve one station at a time

The contract specifies 200 kW per chamber, or 800 kW across the four chambers. Each has heating equipment. They share the car. If chamber A is being unloaded when chamber B reaches its required unloading window, the car still has to handle them in sequence, even if both have finished soaking.

Turning the equipment list into a shift schedule

ItemContract provisionScheduling check
Furnace chambers4 chambers with 1 control zone eachRecord each chamber’s batch number, loading time and planned discharge.
Charging car1 shared carReserve the car from pickup until it is ready for its next task.
Loading and unloading stations1 of eachWhile a coil waits at the loading station, leave space at the unloading station to receive the preceding batch.

Schedule through to the moment the unloading station becomes free

For a busy shift, plot each chamber’s car requirements. Include travel from the preceding station, handover and return. If tasks overlap, check whether charging can be staggered within process limits. Include waiting time if coils from the previous batch still occupy the unloading station.

Coil route: prepare at loading station → transfer to the designated chamber → anneal → transfer to the unloading station.

Check the busiest shift
On the busiest shift, compare each discharge window with car availability and the time the unloading station becomes free.

Use one shift to check the plan

The contract specifies 5.5 tonnes per batch. Suneng’s product information confirms that this includes coils and rack. The buyer supplies the rack. Four chambers heating together does not imply four finished batches in the same hour. Add the net coil weights actually discharged during the shift and count acceptable output under the agreed rules.

During trial production, record each car task’s start and end, when the next chamber was ready, and the reason for waiting alongside the temperature records. This shows whether to adjust charging times, clear a station earlier or reassess the transfer arrangements.

What if we start with two chambers and later use four?

Prepare separate two- and four-chamber schedules, including shifts with mixed grades and soaking times. Supply the permissible discharge windows, station positions and coil batch weights. Suneng can then identify tasks likely to compete for the shared car.

Source: 2020 chamber furnace purchase contract and technical terms, pp. 2, 4, 8–9 and 11. Suneng’s copper-wire annealing configuration explains what is included in the 5.5 tonnes and who supplies the rack.

See Suneng’s fork-handling furnace configurations

Enquiries: +86 130 5298 6814
Email: 997518512@qq.com
Technical authors: Suneng Industrial Furnace Engineering Team and Tang Li