Stainless steel elbows and flanges

Solution treatment of stainless fittings and flanges:
7 tonnes including the basket, immersed within 50 seconds

This 420 kW electric fork-handling furnace solution-treats stainless fittings and flanges. After soaking, the car transfers a 7-tonne loaded basket to the tank. The specified time from first outward movement to complete immersion is at most 50 seconds.

Combined workpiece and basket weight
7 t
Heating power
420 kW
Basket withdrawal to immersion
≤50 s

The 7 tonnes includes the heat-resistant basket and excludes support blocks. Subtract the empty basket weight to obtain net fitting weight.

Project features

The basket carries the entire batch

Load the fittings or flanges into a heat-resistant steel basket and heat them together. All protruding elbows and stacked flanges must remain within the working envelope.

The car transfers the loaded basket

The forks support the basket underneath. After soaking, withdraw it, align it with the tank and lower it. Time from the first outward movement until the last part is fully immersed.

Equipment arrangement and process sequence

Full-line process flow

Select a process card to view its animation

Equipment specifications

ItemProject specification
ModelRX4-420-11 rapid solution-treatment resistance chamber furnace
Heating and control zonesResistance heating, 420 kW, 2 zones
Maximum operating temperature1150 ℃
Furnace temperature uniformity during soaking±10 ℃
Working zone (length × width × height)1.8 × 1.8 × 1.2 m
Full-basket transfer requirement7 tonnes including basket and parts. Maximum withdrawal-to-immersion time: 50 seconds.

Supply responsibilities

Suneng
Supplies the furnace, fork car, drives and controls and carries out installation and commissioning.
Buyer
Supplies the heat-resistant basket and solution-treatment water tank and prepares the site using the foundation information.

Scope of supply

Suneng supplies the resistance-heated solution furnace, door lift, fork charging car and controls. The buyer’s basket carries the same load across the hearth supports, forks and water tank.

Acceptance procedure

Inspection at the manufacturer’s works
After manufacture, both parties check fabrication, assembly, safety and associated equipment under the agreement.
Heating under load on site
Once the empty-furnace test is satisfactory, proceed to heat under load. Acceptance requires meeting the main contract specifications.
Working envelope, load and transfer

1.8 × 1.8 × 1.2 m available for the loaded basket. The stated load includes the parts and the basket. Time from first outward movement until the last workpiece is submerged.

Working envelope, load and transfer

Working envelope, load and transfer
Open original in a new window

Common questions

Loaded basket weight, maximum stacking height and responsibilities for the equipment.

Can it hold 7 net tonnes of pipe fittings?

The 7 tonnes includes the basket. Deduct its empty weight to obtain the net weight of fittings.

How high can the basket be loaded?

The working height is 1.2 m, with a length and width of 1.8 m each. Include stacked flanges and protruding elbows when measuring the loaded basket.

Does the same party supply the furnace, basket and tank?

Suneng supplies the solution furnace and fork charging car. The buyer supplies the heat-resistant basket and water tank.

Reference: 2017 purchase contract and technical agreement for the rapid solution-treatment resistance chamber furnace. The load and transfer interval follow Suneng’s published product information.