A batch of stainless steel pipe fittings

Gas-fired solution treatment of stainless fittings with whole-batch transfer to water

Suneng’s gas-fired fork-handling furnace uses a rail-mounted car to transfer the fittings and fixtures to water together. In this project, the buyer supplies both the solution-treatment tank and the trays.

Rated operating temperature
1200 ℃
Maximum temperature
1250 ℃
Gas burners
8 units

The temperatures and burner arrangement are from the contract appendix. Select the actual solution-treatment temperature for the material and process.

Project features

Whole-batch transfer of fittings at the furnace door

Heat the fittings on a tray. After soaking, the car lifts out the parts and fixtures together and lowers them into the buyer’s solution-treatment water tank.

Furnace-side piping supplied with the equipment

Suneng supplies the furnace-side natural-gas piping, valves, air ducts and fan. The combustion system has 8 burners rated at 450 kW each.

Equipment arrangement and process sequence

Full-line process flow

Select a process card to view its animation

Equipment specifications

ItemProject specification
Equipment listed in the contractGas-fired rapid solution-treatment chamber furnace
Quantity1 set
Effective chamber dimensions (length × width × height)5,200 × 2,400 × 1,900 mm
Rated batch load8 tonnes per batch excluding support blocks
Temperature zones4 zones, each controlling 2 burners
Furnace temperature uniformityWithin ±10 °C during soaking
Workpieces and mode of operationStainless pipe fittings, batch operation
Heating methodNatural gas with combustion and air-supply systems
Transfer at the furnace doorFork car lifts parts and fixtures out and lowers them into the solution-treatment water tank
Gas burners8 burners at 450 kW each
Operating temperatureRated operating temperature 1,200 °C; maximum 1,250 °C

Supply responsibilities

Suneng
Provides foundation design, furnace and drives, gas and air systems, installation and commissioning.
Buyer
Supplies the quench tank, trays and fixture blocks, constructs foundations and embedded items, and provides the cable to the low-voltage distribution cabinet.

Scope of supply

Supplier’s scope includes the furnace, door lift, fork car and drive, sealing system and operating platform, gas piping and valves, combustion air, burners, electrical controls and equipment documentation.

Acceptance procedure

Factory inspection before dispatch
Once the equipment is manufactured, the supplier invites the buyer to the works to inspect fabrication, assembly and associated equipment.
Installation and commissioning under load
Install and commission once the site is ready, then check the technical parameters under load. Acceptance is against the contract specifications.
Gas-fired solution treatment for pipe fittings

Place the pipe fittings on the tray. The gas-fired furnace heats and soaks the batch. The fork car carries parts and fixtures out together, then lowers them into the buyer’s water tank. Natural gas, combustion air, burners and electrical controls. The appendix specifies eight 450 kW burners.

Gas-fired solution treatment for pipe fittings

Gas-fired solution treatment for pipe fittings
Open original in a new window

Common questions

Workpieces, gas equipment and actual consumption per tonne.

Are the tank and trays ordered separately?

The buyer provides both. The contract equipment list assigns the tank to the buyer. Suneng’s engineering records confirm the buyer also supplies the trays. Suneng supplies the charging car with the furnace.

Who provides the gas piping, fan and water tank?

The technical documents assign the gas piping, valves, air duct and fan to the supplier. The buyer provides the water tank.

Does this contract give actual gas consumption per tonne of fittings?

The available records do not include metered gas and corresponding net fitting weight by batch. The related article gives the conditions for the hourly design figures and explains how to calculate consumption from matched gas and weight records.

Reference: 2018 purchase contract and technical documents for the gas-fired rapid solution-treatment chamber furnace. The equipment list assigns the tank. The main parameters cover chamber dimensions, load, controls and burners. Tray responsibility follows Suneng’s engineering check.