Empty furnace or loaded furnace
Record the workpiece, loading arrangement and load used in the test. Empty-furnace results cannot replace loaded production verification.
Engineering guide
Establish comparable test conditions, locate the cause and verify the correction under the agreed load.
Discuss Your RequirementsDo not begin by adjusting the controller alone. First fix the test conditions, then check measurement circuits, heating zones, circulation and flow guides, door seals, the lining and loading pattern. Verify the correction using comparable project conditions and retain the original measurement records.
Record the workpiece, loading arrangement and load used in the test. Empty-furnace results cannot replace loaded production verification.
Agree the number and location of test points, holding period and sampling method. Without consistent conditions, before-and-after temperature differences may not show the effect of a correction.
Check sensor placement, the measurement circuit, instruments and calibration records before treating a displayed temperature as reliable evidence.
Check measurement circuits, sensor locations and calibration. A single stable display does not establish uniform temperature throughout the working zone.
Check heating zones, heating capacity, circulation, flow guides, door sealing and lining condition in relation to those locations.
Review the workpiece, loading density and arrangement, airflow obstruction and process conditions. Evaluate the furnace and its load together.
Retain the test conditions, point locations, time series, instruments and calibration status. Record the corrective work and any remaining deviations.
Specify whether acceptance uses an empty or loaded furnace, measurement locations, holding time, instruments and the applicable standard and edition. Temperature accuracy and uniformity limits must be agreed for the project.
Repeat the agreed test after correction. Controller settings, configuration changes or an isolated reading do not by themselves prove improved uniformity.
It may be part of the work, but the measurement, heating, circulation, sealing, lining and loading conditions must also be checked.
First check that the earlier and later tests used comparable instruments, measurement locations, loads and process conditions. Then investigate the remaining physical and control causes.
State empty or loaded conditions, measurement points, holding time, instruments and calibration, applicable standards and project limits. Keep the raw test records and correction results.