Drawings and actual condition
Compare the drawings with the installed furnace and review maintenance and fault records. Identify concealed areas that can only be checked after shutdown, and define how unexpected findings will be handled.
Engineering guide
Separate the overall project schedule from the production shutdown and resolve uncertain interfaces before work starts.
Discuss Your RequirementsEstablish the old furnace condition and the scope of work before committing to a shutdown date. Plan diagnosis, design, procurement and prefabrication separately from removal, installation, dry-out, commissioning and loaded acceptance. Hidden damage, unclear interfaces and unavailable test conditions can all extend the production interruption.
Compare the drawings with the installed furnace and review maintenance and fault records. Identify concealed areas that can only be checked after shutdown, and define how unexpected findings will be handled.
Check the lining, heating, circulation, controls, mechanisms and loading process together. List utility connections, physical interfaces and the party responsible for each.
Agree how scope changes are assessed and approved. Where returning to the previous configuration is feasible, define the recovery conditions before the changeover.
Confirm the required outcome, inspection findings, technical scope, drawings and acceptance conditions. Unresolved site conditions should remain visible in the schedule assumptions.
Check component lead times, manufacturing, factory checks and work that can be completed before shutdown. Coordinate access and deliveries with the site team.
Allow for removal, lifting, installation, utility connections and work by other contractors. Include an agreed response to concealed defects discovered during removal.
Plan any material-specific dry-out, cold and hot commissioning, and loaded acceptance. Reserve suitable workpieces, operators and measurement equipment for the tests.
Record the baseline load, process, measurement locations and instruments. Test the modified furnace under the agreed conditions so configuration changes can be distinguished from demonstrated results.
Resolve deviations and hand over updated drawings, programs, settings, maintenance information and test records. Installation completion alone does not establish readiness for stable production.
Site diagnosis, prefabrication and staged changeovers may reduce disruption where feasible. Zero downtime cannot be promised before the scope, interfaces and operating conditions are established.
Estimate removal, installation, interfaces, concealed work, dry-out and loaded verification for the actual project. An undefined work scope cannot support a reliable fixed shutdown duration.
No. Design, procurement, manufacture and prefabrication can precede the shutdown. The overall schedule must identify these phases separately.
Based on Suneng’s existing Chinese engineering guide. Project examples retain their original design and acceptance limits. English content updated .
Discuss your project
Share the available information below. Mark anything unknown so it can be clarified during the technical discussion.